No Problems at Fukushima From Weekend Quake

July 12, 2011

Plant Status

• An earthquake of magnitude 7.3 struck northeast Japan Sunday morning, prompting tsunami warnings for the coast, including Fukushima prefecture. Tokyo Electric Power Co. ordered workers at the Fukushima Daiichi plant to move to higher ground and suspended the transfer of low-level contaminated water from the plant to a large steel storage barge. However, no problems at the plant were reported after only a small tsunami wave reached the coast. Cooling water injections into reactors 1, 2 and 3 and nitrogen injections into reactors 1 and 2 continued as normal.

• TEPCO suspended operation of its water decontamination system for 12 hours Sunday to repair a leak in the system. The continued operation of the system is crucial to establish a circulatory cooling system for the reactors and to decontaminate and reduce the water accumulating in the reactor building basements. TEPCO has set a July 17 deadline to establish stable cooling for the reactors. As of July 10, the system has treated more than 18,000 metric tons of contaminated water.

• TEPCO has confirmed that an entry point is available to allow nitrogen injection into reactor 3’s pressure containment vessel. The injection of the inert gas will help prevent the potential for a hydrogen explosion. TEPCO reported to the Nuclear and Industrial Safety Agency July 11 on its preparations for the injection, which is to be started “as early as possible.”

• TEPCO is preparing to restart the fuel pool circulating system for reactor 4, after checking that a kink in the reactor heat removal system piping will not block the flow of water. The system is expected to be in service by the end of July. The company sampled the water in reactor 3’s fuel pool and concluded that boric acid injections have helped to prevent corrosion of the aluminum fuel racks. The issue became a concern when concrete debris in the pool caused the water to become more alkaline.

Industry/Regulatory/Political Issues

• A long-term roadmap drafted by Japan’s Nuclear Safety Commission and TEPCO calls for the removal of melted fuel from the reactors to begin in 2021, provided the technology required for the task has been developed. Damage to the reactor containment vessels will have to be repaired before the fuel can be removed. Dismantling the reactor buildings after the fuel has been removed will likely take several decades.

• TEPCO officials released the results of a detailed simulation of the tsunami that struck the Fukushima Daiichi and Daini plants on March 11. The analysis showed that the wave reached a height of 13 meters (42.7 feet) at the Daiichi plant and 9 meters (29.5 feet) at the Daini plant.

• At a press conference Monday clarifying the government’s position on restarting Japanese nuclear reactors, Chief Cabinet Secretary Yukio Edano stressed that nuclear safety should be given priority over the issue of whether there will be enough electricity to meet demand. Last week Prime Minister Naoto Kan and Minister for Nuclear Crisis Management Goshi Hosono agreed said that “stress tests” assessing the plants’ safety response to severe accidents should be one of the requirements for restarting the reactors, along with routine safety checks. Edano said a first stage would check plants awaiting restart after scheduled maintenance, and the second phase would be for all plants, including those currently operating.

• The Japanese government is requesting parliamentary approval of a second supplementary budget of two trillion yen ($24.5 billion) for nuclear damage compensation, health checks and radiation monitoring. A previous supplementary budget was used for accident recovery and debris removal work.

• Fukushima prefecture officials are inspecting a cattle farm in Minami-Souma city after elevated levels of radioactive cesium were found in 11 cows shipped from the farm to a Tokyo meat processing firm.

Media Highlights

• A Reuters article reported Saturday that Japanese Prime Minister Naoto Kan said it will take decades to clean up and decommission the crippled Fukushima nuclear plant.

• CNN World reported on the Sunday earthquake that prompted tsunami advisories and evacuations of workers at Fukushima Daiichi that were later canceled.

Upcoming Events

• The NRC task force reviewing agency processes and regulations in light of the accident at Fukushima will brief the commissioners on its report at a public meeting July 19. The report is to be released to Senate and House committees July 12. NRC Chairman Gregory Jaczko will speak at the National Press Club in Washington, D.C., on July 18.

Comments

Popular posts from this blog

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Why Ex-Im Bank Board Nominations Will Turn the Page on a Dysfunctional Chapter in Washington

In our present era of political discord, could Washington agree to support an agency that creates thousands of American jobs by enabling U.S. companies of all sizes to compete in foreign markets? What if that agency generated nearly billions of dollars more in revenue than the cost of its operations and returned that money – $7 billion over the past two decades – to U.S. taxpayers? In fact, that agency, the Export-Import Bank of the United States (Ex-Im Bank), was reauthorized by a large majority of Congress in 2015. To be sure, the matter was not without controversy. A bipartisan House coalition resorted to a rarely-used parliamentary maneuver in order to force a vote. But when Congress voted, Ex-Im Bank won a supermajority in the House and a large majority in the Senate. For almost two years, however, Ex-Im Bank has been unable to function fully because a single Senate committee chairman prevented the confirmation of nominees to its Board of Directors. Without a quorum

NEI Praises Connecticut Action in Support of Nuclear Energy

Earlier this week, Connecticut Gov. Dannel P. Malloy signed SB-1501 into law, legislation that puts nuclear energy on an equal footing with other non-emitting sources of energy in the state’s electricity marketplace. “Gov. Malloy and the state legislature deserve praise for their decision to support Dominion’s Millstone Power Station and the 1,500 Connecticut residents who work there," said NEI President and CEO Maria Korsnick. "By opening the door to Millstone having equal access to auctions open to other non-emitting sources of electricity, the state will help preserve $1.5 billion in economic activity, grid resiliency and reliability, and clean air that all residents of the state can enjoy," Korsnick said. Millstone Power Station Korsnick continued, "Connecticut is the third state to re-balance its electricity marketplace, joining New York and Illinois, which took their own legislative paths to preserving nuclear power plants in 2016. Now attention should